On behalf of N.V. Nederlandse Gasunie, De Romein Group executed the Deventer OLS project. This project was divided into three sub-projects: relocating the testing area & reorganizing the warehouse, optimizing the housing conditions, and expanding the assembly hall.
For this project, we carried out the following tasks:
Parking Lot
- removal of the existing paving
- supply and installation of drainage and catch basins
- grading to the construction height
- finishing the sand bed
- supply and installation of approximately 4000 m2 of concrete pavers
- supply and installation of approximately 750 meters of concrete curb
- supply and installation of street lighting
Assembly Hall Construction
- supply and installation of steel pipe piles
- installation of the foundation beam
- supply and placement of 63 tons of steel structure
- supply and installation of approximately 1500 m2 of cladding
- supply and installation of approximately 600 m2 of roofing
- supply and placement of 172 concrete slabs
- supply and placement of a 20-ton overhead crane
Internal Renovation of Canteen and Offices
- demolition and removal work
- supply and installation of floor tiles
- supply and installation of carpet tiles
- supply and installation of sliding partitions
- supply and installation of the kitchen unit
Internal Renovation of Warehouse and Welding Area
- demolition and removal work
- installation of approximately 150 m2 of concrete floor
- supply and placement of approximately 150 m2 of aerated concrete walls
- supply and placement of approximately 110 m2 of hollow core slab flooring
- application of coating on concrete floors
- supply and placement of steel staircase and railing
- supply and placement of warehouse lift
- supply and placement of overhead door
Internal Renovation of Testing and Workshop Area
- demolition and removal work
- supply and installation of steel pipe piles
- installation of foundation beams
- installation of approximately 250 m2 of concrete floor
- supply and placement of approximately 275 m2 of cellular concrete block walls
- application of coating on concrete floors
- supply and installation of frames
- supply and placement of steel staircase and railing
- supply and placement of overhead door
- supply and placement of a 5-ton overhead crane
The Challenge
In the warehouse and testing area, we worked with multiple concrete floors treated with a specific type of liquid-tight coating. This makes the floor highly durable and slip-resistant.
Height Difference
The height difference on the site posed a challenge. We addressed this by installing a retaining wall. Afterward, the construction of the assembly hall could begin.
Parking Lot
A portion of the parking lot needed to remain accessible for Gasunie employees during the work process. Therefore, we staged these activities in phases.