TENP III (Trans Europa Naturgas Pipeline)

De Romein has been hired by Streicher to provide support for civil works on the TENP III (Trans Europa Naturgas Pipeline) project, including the replacement of a DN1000 pipe over 51 km (Sections 1 and 2) between the stations of Mittelbrunn and Klingenmünster in the Rheinland-Pfalz region of Germany.

These activities included the removal of the existing TENP I pipeline - excavation and backfilling for the removal in collaboration with a team from Streicher, digging the trench for the new pipeline, installing bedding and backfilling with padding equipment, laying telecom HDPE pipes, and finally, the complete restoration of the ROW.

Currently, excavation work for the existing pipe is progressing well in sections 1 and 2, with nearly 20 km completed.
De Romein will begin excavation activities for the new TENP III pipeline in mid-May.

TENP III (Trans Europa Naturgas Pipeline)
Photos